Table 1 The identified activities within the three end-to-end registration processes employed by SAHPRA between 2011 and 2022 and the median timelines of the activities

From: Regulatory registration timelines of generic medicines in South Africa: Assessment of the performance of SAHPRA between 2011 and 2022

 

Allocation timeframe

Preparation of assessment reports

Peer review process

Quality assurance

List of queries to the applicant

Applicant time

Cycle

Median time in calendar days for registration activities for the MCC process (2011–2017)

1

682

201

-

74 (0 finalised)

347

2

186

62

72 (168 finalised)

76

3

56

76

74 (116 finalised)

76

4

31

47

32 (35 finalised)

56

5

16

16

20 (6 finalised)

-

 

Median finalisation timeline

1470

 

Median registration timeline

2092

Cycle

Median time in calendar days for registration activities for the BCP (2019–2022)

1

278

63

29

35

30 (0 finalised)

84

2

22

35

15

30

15 (30 finalised)

33

3

10

30

10

20

15 (58 finalised)

22

4

7

7

5

10

10 (25 finalised)

20

5

2

11

5

15

5 (13 finalised)

 

Median finalisation timeline

501

 

Median registration timeline

591

Cycle

Median time in calendar days for registration activities for the RBA phase 1 pilot study (2021–2022)

1

431

5

8

2 (3 finalised & 2 withdrawn)

25

2

2

2

6

1 (44 finalised)

18

3

1

1

7

1 (6 finalised & 2 withdrawn)

10

4

1

1

7

1 (4 finalised)

 

Median finalisation timeline

68

 

Median registration timeline

511

Cycle

Median time in calendar days for registration activities for the RBA phase 2 pilot study (2022)

1

 ~ 2 years

5

8

1 (6 finalised)

28

2

2

2

7

1 (102 finalised & 1 withdrawn)

15

3

1

1

7

1 (44 finalised & 2 withdrawn)

12

4

1

1

5

1 (7 finalised)

 

Median finalisation timeline

73

 

Median registration timeline